Timeline: Clean Snowmobile Challenge

Clean Snowmobile Challenge
Date Event Event
9–Nov–05 Fuel sys ordered Polaris Dyno setup completed
10–Nov–05 2nd engine and Arctic Cat Parts Ordered  
1–Dec–05 Order Cat  
6–Dec–05 Procedures and Research
completed
 
23–Dec–05 Injector Installation completed  
9–Jan–06 Mapping Old Sled Running
10–Jan–06 Catalyst here  
16–Jan–06 Fuel Choice Due Team Program info due
21–Jan–06 Benson Racing  
22–Jan–06 Benson Racing  
28–Jan–06 Testing Emissions, Noise, Accel, Endurance, Handling
4–Feb–06 Testing Emissions, Noise, Accel, Endurance, Handling
3–Mar–06 Tech paper due TICA due
13–Mar–06 Competition Starts