| Task Description | Scheduled Date |
| Mock engine running on dyno (stock ecu, gasoline) | 27-Sep |
| Suspension/Chassis Design Due | 10-Oct |
| Order Tubing | 24-Oct |
| Start fabrication of intake and exhaust systems | 1-Nov |
| Construct a-arms | 7-Nov |
| Testing of Intake and Exhaust systems | 22-Nov |
| Completion of Chassis | 12-Dec |
| Final Intake and Exhaust Design Chosen | 23-Dec |
| Rolling/ Steering Chassis | 23-Jan |
| Install Brake Components | 1-Feb |
| Install Axles/ Diff. | 20-Feb |
| Drive train installed | 20-Feb |
| Shifter Installed | 6-Mar |
| Cooling system installed | 20-Mar |
| Fuel system installed | 20-Mar |
| In vehicle testing begins | 3-Apr |
| Competition Begins | 17-May |